Progress on the new clubhouse continues.
All in ground services have been installed and tested.
The sub floor steel has been installed and covered with concreate.
Stadium Solutions are due back on site 14th November to commence the roof and wall cladding, creating a dry work area for the brick layers to return and start constructing the internal rooms.
The club is still looking to boost funds to kit out the internals of the clubhouse and would like to invite people to have their name or message be on show within the new clubhouse for ever more, for just £20, details below.